The UK Carbon Border Adjustment Mechanism is a charge on the direct emissions embodied in imported aluminum, cement, fertilizer, hydrogen, and iron and steel. Legislated in Part 5 of the Finance Act 2026, it applies to goods imported on or after Jan. 1, 2027. The importer owes the charge, calculated as the tonnes of CO₂e embodied in the goods multiplied by a rate tied to the UK Emissions Trading Scheme.

Why It Matters for Manufacturers

The U.K. and EU mechanisms share a name and a purpose, but a manufacturer supplying both markets faces two sets of rules. The U.K. version counts direct emissions only, for every sector, including the emissions of in-scope precursors. It does not cover electricity. Its threshold is set by value rather than mass. Importers pay the charge directly with a return, with no certificates to buy.

The rate is set quarterly. It starts from the average UK ETS auction price in the previous quarter, adjusted for the free allocation U.K. producers in the same sector receive, and the government publishes it at the start of each quarter.

The data request works the same way as in the EU. An importer can use government default values or the producer’s actual verified emissions. Verification requires an independent verifier accredited to ISO 14065 and ISO/IEC 17029, with physical site visits and a 5 percent materiality threshold.

Importers can claim relief for a carbon price effectively paid where the goods were made, net of any rebates or support, and capped at the UK CBAM liability. The EU ETS is on the provisional list of qualifying schemes. For a manufacturer with EU plants that ship to the U.K., the carbon cost those plants already pay can reduce what its U.K. customers owe.

U.S., U.K. and EU Applicability

A U.S. manufacturer exporting covered goods to the U.K. owes nothing directly. Its U.K. customer owes the charge and will ask for emissions data. With no federal carbon price in the U.S., there is no U.S. carbon price to claim as relief.

Neither the U.K. nor the EU mechanism exempts goods from the other’s territory. The U.K. policy summary states that no jurisdiction is currently exempt from the UK CBAM.

Current Status

Last updated: Oct. 5, 2026

  • An importer must register if it expects to import £50,000 or more of covered goods within the next 30 days, or if it imported £50,000 or more in the previous 12 months, checked on the first day of each month from Jan. 1, 2027. For 2027 only, the registration deadline is extended to Jan. 31, 2028.
  • 2027 is a single annual accounting period, with the return and payment due May 31, 2028. From 2028, accounting periods are quarterly. The first quarterly return and payment, for Q1 2028, is due July 31, 2028.
  • Four sets of regulations made in July and September 2026 cover administration, the rate and carbon price relief, transitional rules, and emissions and verification. All take effect Jan. 1, 2027.
  • HMRC published a provisional list of qualifying carbon pricing schemes for relief Aug. 27, 2026 and updated it Sept. 9, 2026. The list includes the EU ETS.